How to Calculate Deck Posts: Formulas & Spacing Rules
Deck support posts transfer the gravity loads of the deck, furniture, and occupants from the supporting beams down into concrete footings and the soil. Determining post quantities requires calculating the number of spans along your beam lines.
1. Bays Along Beam Line = β Beam Length Γ· Post Spacing β
2. Posts Per Beam Line = Bays Along Beam Line + 1
3. Ledger-Attached Deck Posts = Posts Per Beam Line (1 Beam Line)
4. Freestanding Deck Posts = 2 Γ Posts Per Beam Line (2 Beam Lines)
5. Perimeter Layout Posts = (2 Γ Length Posts) + (2 Γ Width Posts) - 4 Corners
6. Cuts Yielded Per Stock Piece = β Stock Lumber Length Γ· Deck Cut Height β
7. Commercial Stock Posts to Purchase = β (Base Posts Γ· Cuts Per Piece) Γ (1 + Waste % Γ· 100) β
Original Worked Example (Verified Arithmetic)
Example: 20 ft Length Γ 12 ft Width Ledger-Attached Deck
- Inputs: 20 ft Length, 12 ft Width, 8 ft Post Spacing, 4 ft Deck Height, 8 ft Stock Lumber, 10% Waste, Ledger-Attached layout.
- Beam Length: 20 feet.
- Bays along Beam: β20 ft Γ· 8 ftβ = 3 bays.
- Base Support Posts: 3 bays + 1 = 4 support posts along outer drop beam.
- Cuts per Stock Piece: β8 ft stock Γ· 4 ft heightβ = 2 posts per 8 ft board.
- Base Stock Boards: β4 posts Γ· 2β = 2 stock boards.
- With 10% Waste: β2 Γ 1.10β = 3 stock boards to purchase (+1 extra board).
- Total Linear Material: 4 posts Γ 4 ft = 16.0 linear ft (with 10% waste = 17.6 linear ft).
- Concrete Footing Benchmark: 4 footing holes at \$15β\$38 per post = \$60.00 to \$152.00.
4Γ4 vs 6Γ6 Deck Post Sizing Guidelines
| Post Dimension | Maximum Height (IRC Code) | Recommended Beam Connection | Code Suitability |
|---|---|---|---|
| 4Γ4 Post (3.5" Γ 3.5") | Up to 6β8 feet (check local code) | Notched post cap bracket | Permitted on low, single-level ground decks; prohibited in many jurisdictions for multi-story decks. |
| 6Γ6 Post (5.5" Γ 5.5") | Up to 14 feet | Direct bearing notched shoulder or Simpson post cap | Standard requirement for elevated decks, multi-ply built-up beams, and modern residential building permits. |